DOW in progress
In this page you can see the progress by TASK and study site according to the Document Of Work (DOW); our contractual context with the agencies*.
TASK 1
D1: Due by September 2016, lead by Vanderlinden.
D6: Due by September 2016.
Draft version ok July 15th.
Title: Adaptation Interdisciplinarity Challenges: Insights from the community of Uummannaq, Greenland
Authors: Cordier, Baztan, Huctin et al., final version expected September the 15th to be sent to: http://www.ecologyandsociety.org/
D8: Due by January 2017.
M6: Done and available on line for Uummannaq, Sénégal, Cocagne and Tiksi, need to be completed by the others study sites.
M15: Done and available on line for Uummannaq, Sénégal, Cocagne and Tiksi, need to be completed by the others study sites.
TASK 2
D2: Due by July 2016, lead by Surette.
M3: Done and available on line for Uummannaq, Sénégal and Tiksi, need to be completed by the others study sites.
M7: Done and available on line for Uummannaq, Sénégal and Tiksi, need to be completed by the others study sites.
M12: Done for Uummannaq, Tiksy and Sénégal, need to be completed for the other study sites and uploaded on the web site.
TASK 3
D3: Due by September 2016, lead by Baztan & Kofinas.
M4: Done and available on line for Uummannaq, Sénégal and Tiksi, need to be completed by the others study sites.
M8: Done for Uummannaq, Tiksy and Sénégal, need to be completed for the other study sites and uploaded on the web site.
M13: Done for Uummannaq, Tiksy and Sénégal, need to be completed for the other study sites and uploaded on the web site.
TASK 4
D4: Due by July 2016, lead by Kennedy.
M5: Done and available on line for Uummannaq, Sénégal and Tiksi, need to be completed by the others study sites and uploaded on the web site.
M9: Done and available for Uummannaq, Sénégal and Tiksi, need to be completed by the others study sites and uploaded on the web site.
M14: Done and available for Uummannaq, Sénégal and Tiksi, need to be completed by the others study sites and uploaded on the web site.
TASK 5
M10: Done.
M17: Done.
M19: Work in progress, due by September 2016.
TASK 6
D7: Due by January 2017.
M19: Due by October 2016.
* The "agencies" are the national research agencies involved in the "Belmont Forum International Opportunity Fund"